Electricity supply to the Lagos area has returned to the level it was at before last week's disruption, the Minister of Power, Joseph Olasunkanmi Tegbe, said on Monday, November 9, after engineers repaired the vandalised Benin–Egbin 330kV transmission line.

This restoration helped to bring the total power supply to the Lagos Complex to over 1,000 megawatts, effectively normalising to the condition before the disruption.— Joseph Olasunkanmi Tegbe, Minister of Power

The outages hit parts of Lagos, Ogun, Oyo, Kwara and the Federal Capital Territory. By Sunday night, supply had been restored to Ajah, Lekki, Ikoyi, Magodo and Ikeja, Vanguard reported.

What went wrong

The minister blamed three things at once: planned maintenance at Egbin Power Station, which he said supplies about 16 per cent of the grid's power; gas shortages at thermal plants; and sabotage of transmission lines. Grid operators used load shedding to manage the shortfall. Power allocated to the distribution companies fell to about 2,926MW on November 5.

The Nigerian Independent System Operator (NISO) also pointed to limited gas for thermal stations and low water levels at hydro plants. NNPC Limited disputed the gas explanation, saying its pipeline network remained available and that gas supply was "not a challenge".

A missed 72 hours

Tegbe had promised last week that supply would be restored within 72 hours, a deadline that passed before the line was fixed. "Let me start by telling Nigerians that I feel their pain," he said. He told reporters that stable electricity was three to five years away, depending on new investment in generation and transmission.

The Ministry of Power said it was working with the generation companies, the system operator, the Transmission Company of Nigeria and the DisCos to restore full supply to areas still affected.

Sources: statements by the Minister of Power reported by Vanguard and allAfrica (November 9–10, 2026); NNPC Limited and NISO statements reported by allAfrica.